SS> Maintenance> PM Security
        
            PM Security
         
        Summary
        
         
        The Task Security window is used to set up security on Project Management 
module tasks. This keeps users or user groups from attaching a PM task to 
transactions in specific modules or the entire application. Users will only be 
	able to attach a PM module task to their timesheets or to invoices if that 
	PM tasks is manually enabled using the PM Security window.
         
        Security can be set up by user or user group. Security set up on a user will 
override the security that is set up on a user group. For example, if an employee 
is attached to both a user and a user group, and there is PM security on both, 
the PM security on the user will apply. This allows you to assign users to user 
groups and then customize the security on each user by assigning specific 
security at the user level.
         
        When a user or user group is restricted from using a task code in a module 
(for example, a user is forbidden from attaching a certain task code to AP 
invoices), that task code will not display in the selection window that is 
opened from the Task Code field labels. If the user manually enters the 
forbidden task code into a Task Code field, they will receive an error 
message when they try to save the new record.
         
        You should limit access to the PM Security window using the Menu Security feature
(SS> Maintenance> Menu Security).
         
        When a user creates a task code using the Task Maintenance window (PM> 
Maintenance> Task), the user will automatically have system wide access to that 
task code. For example, if a user creates a task code in the Task Maintenance 
window, they will be able to attach that task code to their timesheet in the 
Payroll module or to an AP module invoice line item.
         
        You can also limit access to PM module task codes that are attached to 
	transactions by locking the task (PM> Maintenance> Task> General tab> Locked toggle). Locked tasks cannot be attached to 
	transactions (for example, AP invoices, PR timesheets, etc.).
	Click here for information on locking a task.
         
        Step by Step
        
         
        1     View the PM security set up on a user or user 
group.  
            
                 
                
                    - Open the Task Security window (SS> Maintenance> PM Security).
 
                    - PM security can be set up by both user and user group. Use the User or 
	User Group icon at the top of the page to select the type of security you 
	would like to create. Security set up on the user level will override 
	security set up on the user group level.
 
                    - Select a user or user group from the drop-down menu.
 
                    - All of the PM module task codes will display in the grid, along with the 
	security defined on each.
 
                
             
         
         
        2     Define security on the task codes.  
            
                 
                
                    - The SS, AP, DS, PR, PO,  GL and IC columns represent the modules in the 
	application where Project Management module task codes can be attached to 
	transactions. Check the toggle to enable the task code in that module for 
	the user group or user selected in the drop-down menu at the top of the 
	window.
 
                    
                        - GL - PM module task codes can be attached to journal entry line 
		items in the Journal Entries batch process (GL> Journal Entries).
 
                        - AP - PM module task codes can be attached to invoice line items in 
		the AP Invoices batch process (AP> Invoices), and manual check line 
		items (AP> Manual Checks).
 
                        - DS - The Departmental Services module has not been implemented, so 
		this toggle currently has no function.
 
                        - PR - PM module task codes can be attached to timesheets (PR> 
		Timesheets) and timecard line items in the Computer Checks and Manual 
		Checks batch processes.
 
                        - PO - PM module Task and Type codes can be attached to Purchase Order or Requisition line items. When the purchase order or requisition is invoiced, the PM Task will display the PO transaction.
 
                        - IC - PM module task and type codes can be attached to an IC Inventory Transaction in order to track materials costs on special projects.
 
                        - SS - The SS toggle is used to enable the task in the entire 
		application. This will put a check in all of the module columns. The SS 
		module toggle also determines if the task will display in the Task Selection 
		window in the Project Management module (PM> Maintenance> Task), and if 
			it can be used in the Purchase Order module.
-  If a user creates a task (PM> Maintenance> Task), this toggle 
			will automatically be checked.
 
 
                        - The PM module overview page has a diagram that displays the 
		processes in the application that create PM module transactions.
		Click here for an overview of the processes 
		in the application that create PM module transactions.
 
                    
                    - You can also use the drop-down menu next to the Enable and Disable 
	icons at the top of the window to make your security selections. Highlight a 
	PM module task code in the grid and then select the security you would like 
	to set using the drop-down menus next to each icon.
 
                    - Press ENTER or click the Save icon 
 to save the security. 
                    - Press ESCAPE or click the Exit icon 
 to close the window. 
                
             
         
         
        
        Springbrook Software
        