UB> Meter Management> Change Outs

Meter Change Out Report

 

Summary

 

The Meter Change Out Report displays a list of meters that have been replaced using a meter change-out service request. The report will display the device that has been removed and the new device that was installed on the customer account, but the devices will not display on the report until the change out service request has been committed (UB> Service Requests> Commit). The report can be filtered by meter read route and date range based on the install date of the new device. The install date of the device is the same as the service date of the service request that performed the meter change out.

 

A meter can be removed from a customer account using a remove device or change out service request, but only meters removed using a change out service request will display on this report. Once a meter change out service request has been committed (UB> Service Requests> Commit), the status of the original meter on the customer account will change from Installed to Removed and the install date of the new meter will be the service date on the service request.

 

Related Links

 

Click here for information on creating a Change Out Device service request.

Click here for information on the Jobs Viewer window.

 

Step by Step

 

1     Open the Meter Change Outs window (UB> Meter Management> Change Outs).