PM> Maintenance> Project
Project Maintenance
Summary
A Project is the highest level of organization in the Project Management module because a project can be
associated with multiple tasks. For example, if you are organizing a parade, you
could set up the parade as a project and then create a task for each job that
needs to be completed. The time card entries and transactions will be posted to
the tasks, but the tasks will be grouped together by project. When you want to
view the progress of a project and the tasks associated with it, generate a Task
by Project Report (PM> Reports> Task by Project).
Project
|
↑
|
↑
|
↑
|
Task
|
Task
|
Task
|
Projects are an optional grouping in the Project Management module. You are not required to attach a
project to a task code.
Related Links
Click here for information on attachments.
Click here for information on Task Maintenance.
Step by Step
1 View the projects.
- Open the Project Selection window (PM> Maintenance> Project).
- The Project Selection window will display all of the projects that have been created in the Project Management
module.
- Use the Active Status drop-down menu to filter the displayed projects by status.
- Highlight a project and press DELETE to delete the selected project. You cannot delete a project that is
attached to a task.
- Projects are attached to tasks using the Task Maintenance window (PM> Maintenance> Task> General
tab> Project field).
- Highlight a project and press ENTER to open the selected project.
- Press INSERT to create a new project. This will open the Project Maintenance window.
2 Create or modify a project.
- Enter a Project Code for the new project. The project code can be up to six alphanumeric
characters.
- You cannot change the project code once the project has been created and saved.
- Enter a description for the project in the Description field. The project description can be up to 32
characters long.
- The Active toggle will be automatically checked on new projects. This toggle allows users to filter out those projects that are no longer active.
- Click the Attachment icon
if you would like to view the documents attached to the project or would like to
attach a document to the project. This will open the Attachments Selection
window.
- Click the Save icon
or press ENTER when complete. The Project will be added to the Project Maintenance
window.
- After the project has been saved, you can attach the project to a task code using the Task Maintenance window (PM>
Maintenance> Task> General tab> Project field).