Summary
The Task Group Maintenance window is used to create and maintain task groups. Task groups are used as
templates when creating new tasks in the Task Maintenance window (PM>
Maintenance> Task). When a task is created, the information attached to the task
group will populate on the new task.
When a task is created, it is assigned a task code. The task code number is composed of two parts: task
group and sub-task, and the format of those parts is defined in the Setup
window (PM> Utilities> Setup> Task 1 Format and Task 2
Format fields). The task group entered in the task code number functions
like a template because the information attached to the task group (PM>
Maintenance> Task Group) will populate on the task code. The sub-task represents
a unique occurrence of the task group. For example, task code 500-0001
represents task group 500 and sub-task 00001.
When creating a new task in the Task Maintenance window (PM> Maintenance> Task), if you enter a new task
group, the new task group will be created in the Task Group Maintenance window
(PM> Maintenance> Task Group).
Related Links
Click here for information on project maintenance.
Click here for information on LEMS code maintenance.
Step by Step
1 View the task groups.
- Highlight a task group in the left section of the window and the Maintenance section will populate with the
information attached to the selected task group.
- Highlight a task group and press DELETE to delete the selected task group.
- Click the Create icon
to create a new Task Group. This will open the Task Group Maintenance Detail window.
2 Create or modify a task group.
- The value in the Description, Begin Date, End Date, Project, Misc 1,
Misc 2 and Misc 3 fields will populate on tasks created using the task group entered in the
Task Group Code field.
- Enter a code in the field labeled Task Group Code.
- The format/character length of the Task Group Code field is defined in the Setup window (PM> Utilities>
Setup> Task 1 Format field).
- When a task is created using the code entered in this field, the information attached to the task group will
populate on the task.
- Enter a description of task group in the Description field.
- When tasks are created using this task group the description will populate on the task,
but you will be able to modify the value. For example, if you enter
“General Engineering” in the Description field, “General
Engineering” will populate on the task but you will be able to customize
the description to read “General Engineering – Main St. Sewer.”
- Enter a date in the Begin Date and End Date field if all tasks of this task group begin and end on a specific date.
- The Project field is used to attach a project to the task group. Click the Project
field label to select a project from a list.
- Projects are the highest level of the PM module hierarchy (Projects> Task>
Task Group and Sub-Task), and generally represent an entity that is associated
with many different tasks. The Task by Project Report will display tasks grouped
and totaled by the project.
- Projects are created and maintained using the Project Maintenance window (PM>
Maintenance> Project).
- The Misc 1, Misc 2 and Misc 3 fields are used to add miscellaneous
information to the task group. Click the field labels to select the
miscellaneous information from a list.
- The miscellaneous fields are used to create user defined sub-categories on task codes. These miscellaneous fields
can be used to sort and filter reports in the Project Management module.
- Miscellaneous information is maintained in the Miscellaneous Maintenance windows (PM> Maintenance> Misc 1,
Misc 2, Misc 3).
- Press ENTER or click the Save icon
when complete to save the task group.